PMP考試每天一練-2023年PMP考試模擬題26
PMP考試練習題一: 由于一臺設備設計規格中的某一項被忽略了而導致項目延期,而趕制此項需要更長的交貨期。為避免這種情況的發生,項目經理在項目規劃期間應完成下列哪一項? A project is delayed because one item in the equipment specification has been ignored. It will require a longer lead time to catch up. To avoid this situation, the project manager should have done which of the following in project planning? A:A 制定應急計劃 prepare a contingency plan B:選擇更為可靠的供應商 select a more reliable supplier C:在識別風險過程上花費更多的努力 spend more efforts on the process of risk identification D:確保該項不在關鍵路徑上 ensure that the item is a not on the critical path PMP考試答案解析:所屬過程組:規劃過程組。所屬知識領域:項目風險管理。出現這種情況識別風險不充分。 PMP考試參考答案:C PMP考試練習題二: 以下哪項不是用于進度控制的工具或技術? A.偏差分析 B.三點估算 C.假設情景分析 D.資源平衡 PMP考試參考答案:B |